Guys:
To get back to the question at hand.....
For final:
A set of approved plans on site.
All paperwork (permit & updates) filed & paid.
All devices installed and energized.
Panel labeled correctly, hopefully.
A lighting outlet in each area (sw recept or fixture) A 'blanked' box is acceptable.
'Hard wired' appliances installed.
(Majority of jobs are gas ranges; the gas appliances are REQUIRED for the gas utility to turn-on the gas service.
Smoke/carbon detectors
and all the other usual stuff.

OK, IF an electric range/oven is on the plans, it HAS to be installed. Dryers are plug-in, so.....
Dishwashers are hard wired, central air CU's must be installed/wired, etc.

THe EC's know not to schedule a 'final' with missing items.

Depending on the situation, we can issue a TCO, but that's another story.

John