So you would hold off final on a cubicle connection? Where often the banks will not fund money until the buildings are finaled?

I've never had a problem getting finaled with a few loose ends. Though I have a couple things going for me that help:

1) Clean up the job. If you have material and tools everywhere the inspector will think you aren't ready.
2) Be honest with the inspector. I tell the inspector what’s left and why its not done. No inspector I know is going to hold up final because the owner’s forklift charger is still shipping.
3) Have everything labeled in print. A label maker makes your job look like you are on top of things. This makes the inspector more comfortable releasing the building.

Inspectors are human too (well for most cities [Linked Image] ). Have the job look professional and be honest with the inspectors and usually they will be helpful on getting the building passed.