Wow! One of my posts went flaming! A first for me. The drawings I received showed a new service riser to refeed the existing 1200.

Someone had already hung a CT cabinet and core drilled the exterior wall, presumably the owner of the green ladder.

The utility had set a new pole complete with 3 spanking new trannies. The other contractor was halted and this is now to be included in my cost. This design will still leave unfused conductors inside the building for about 25 feet. Low voltage at least.

So it is in the repair stage. I may or may not pursue this work. Those primaries evidently come down inside an interior wall as this is in the basement.

I've informed the GC to make SURE the service is killed from the pole before the demolition (sledge hammers and sawzalls) contractor begins.