ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Increasing demand factors in residential
by gfretwell - 03/28/24 12:43 AM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
Do we need grounding?
by NORCAL - 03/19/24 05:11 PM
240V only in a home and NEC?
by dsk - 03/19/24 06:33 AM
Cordless Tools: The Obvious Question
by renosteinke - 03/14/24 08:05 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
1 members (CoolWill), 250 guests, and 13 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#88266 05/25/04 06:07 PM
Joined: Nov 2002
Posts: 558
G
Member
This is a 200a 1ph. UG residential service.

No metallic water lines,interior or exterior. Meterbase is back to back with a 200a main brkr. panel. Short pvc nipple between them. # 4 solid copper from lug in MB down to 2 ground rods 6' apart.

No Ahj here. Homeowner hired a retired elec inspector to look at job and he says the #4 must come from the panel.

Can anyone give me a code art.for this?

Russell

Stay up to Code with the Latest NEC:


>> 2023 NEC & Related Reference & Exam Prep
2023 NEC & Related Reference & Study Guides

Pass Your Exam the FIRST TIME with the Latest NEC & Exam Prep

>> 2020 NEC & Related Reference & Study Guides
 

#88267 05/25/04 06:15 PM
Joined: May 2002
Posts: 1,716
R
Member
Hello Russell, It sounds as though this retired inspector is from an area that is not used to seeing this connection at the meter.

Roger

[This message has been edited by Roger (edited 05-25-2004).]

#88268 05/25/04 06:29 PM
Joined: Nov 2002
Posts: 558
G
Member
Hi Roger.

Thats what I thought. I don't see the difference in this situation.

Russell

#88269 05/25/04 09:18 PM
Joined: Feb 2002
Posts: 840
C
Member
Russell,

The connection to a ground rod doesn't need anything larger than #6 Copper. Nothing wrong with the #4 of course. [Linked Image]

Peter


Peter
#88270 05/25/04 09:47 PM
Joined: Nov 2002
Posts: 558
G
Member
You're right CT. It's just a habit. [Linked Image]

[This message has been edited by ga.sparky56 (edited 05-25-2004).]

#88271 05/27/04 11:13 PM
Joined: Apr 2004
Posts: 60
M
Member
Here in Washington, the meter base is not considered to be accessible to the occupant. Technically, the power company says you need to call and coordinate cutting the seal, there its not really accessible. Therefore, the GEC can not be run from there.

This is a AHJ call, and not an NEC code rule except for a strict interpretation of 250.68 which says the GEC must be accessible.


Mark