They are sure the steel framing was energized by a drywall screw strike and I hear this is the body they needed to require some kind of bonding in these steel studs. They are using "EGC of circuit likely to energize" instead of 250.104(C) that refers to a 250.66 sized jumper. That means a metal box or a plastic box with bonding strap will work.