CharlieE,
Does your utility have access to demand data from metered sites? For instance, if you have a new school of a square footage and certain types of equipment, that you could pull archived data from similar sites and size your transformer based on that information. I know of one in our area who looked at such data to make those decisions (when necessary). Their concern was the initial costs of supplying an oversized transformer and the continuing costs of supplying the magnetizing power to that unit.
I guess where I'm going with this is that if you can nail down the transformer to be used more precisely, it can allow for more
flexibility in what can be done on the customers side of the project.