Good point Nick.

My current project is a 70,000sq.ft. nursing home. We have been running 8 or 9 men most of the time. This is my first experience with a larger crew after years of doing projects with 2 or 3 men.

It is a whole new ballgame. 80% of my time is spent ordering materials, coordinating work with other trades, attending progress meetings, layout, QC, and general supervision.

On the rare day when I can just run some pipe and wire it is a real joy and the day goes by much faster.

GJ