ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
Top Posters(30 Days)
Potseal 11
Recent Posts
600 KW 120/208 3 Phase Y protection
by Yooperup. 07/21/17 09:27 AM
1913 American Electrician's Handbook
by gfretwell. 07/20/17 01:08 PM
Green House wiring
by ghost307. 07/20/17 09:10 AM
Permit Snafus...AHJs and Contractors Jump in
by HotLine1. 07/18/17 08:06 PM
New in the Gallery:
SE cable question
Popular Topics(Views)
239,222 Are you busy
174,623 Re: Forum
167,049 Need opinion
Who's Online Now
0 registered members (), 57 guests, and 9 spiders.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate This Thread
#87648 - 04/01/04 09:26 PM wireway  
big guy  Offline
Member
Joined: Dec 2003
Posts: 59
pa
I have seen this done and can't find any
violations.Can you put EMT through a wireway
at a right angle
Example
If i have a panel with a wireway above it (horizontal)can i run EMT Vertically through
the wireway right into the panel.
thanks big guy


2017 / 2014 NEC & Related Books and Study Guides

#87649 - 04/02/04 06:06 AM Re: wireway  
iwire  Offline
Moderator
Joined: Jan 2003
Posts: 4,391
North Attleboro, MA USA
I do not know any violation with that.

Looks bad but sometimes the only option.


Bob Badger
Construction & Maintenance Electrician
Massachusetts

#87650 - 04/03/04 10:39 PM Re: wireway  
PCBelarge  Offline
Member
Joined: Jun 2003
Posts: 681
Dobbs Ferry, NY, USA
725.55(C) permits raceways within enclosures. I do not see where this is prohibited, and as Bob has said may be the only way to reach a panel.

Pierre


Pierre Belarge

#87651 - 04/04/04 01:04 AM Re: wireway  
stamcon  Offline
Member
Joined: Mar 2001
Posts: 329
So San Francisco CA


#87652 - 04/06/04 05:58 PM Re: wireway  
big guy  Offline
Member
Joined: Dec 2003
Posts: 59
pa
yes that is what i has talking about
Would you use the O.D of the pipe as your
20%. 376.22 02 code thanks


#87653 - 04/09/04 11:48 AM Re: wireway  
Cobtronics  Offline
Member
Joined: Jul 2003
Posts: 18
Vermont
We do this all the time in the plant I'm in. Many advantages: 1)Makes for a snap to add new pipes in limited spaces. 2) Can run new pipe and wire into gutter w/o shutting down the panel - only shut down for final pull and connect. 3) You run outta KOs on the top fast and the pipe job gets ugly when you have to snake 15 - 20 runs into the side KOs - even pull ells don't help sometimes. On jobs where this wasn't done, the panel top might have been made of chicken wire for all the strength it had after it was punched.
We deduct the volume of the pass thrus from the volume of the box for fill calcs, but that is the engineer's or AHJ's call to make initially.



Member Spotlight
lil suzi
lil suzi
Midwest
Posts: 57
Joined: August 2003
Show All Member Profiles 
Featured:

2017 NEC and Related
2017 NEC
Now Available!

Shout Box
Powered by UBB.threads™ PHP Forum Software 7.6.0
Page Time: 0.011s Queries: 14 (0.002s) Memory: 0.7753 MB (Peak: 0.9212 MB) Zlib enabled. Server Time: 2017-07-23 04:53:02 UTC