ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
UL 508A SPACING
by ale348 - 03/29/24 01:09 AM
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
Do we need grounding?
by NORCAL - 03/19/24 05:11 PM
240V only in a home and NEC?
by dsk - 03/19/24 06:33 AM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
1 members (ale348), 302 guests, and 14 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#58830 11/21/05 08:23 PM
Joined: Sep 2005
Posts: 34
K
kdal Offline OP
Member
Hello everyone
Posted SEU meant SER
I have a few questions regarding service entrance cable.
Is it possible to come from the meter can through the wall and up without violating the bend radius. The walls are framed with 2 x 4’s.
The actual diameter of the conductors in 4/0 aluminum SE cable appears to be aprox. 5/8 to 3/4 an inch. 3/4 x 5 = 3 and 3/4 inch bending radius.
Also this puts the cable very close to the finished surface. Wouldn’t this require nail plates?
I have seen this done many times and always passed inspection. I am interested in doing things proper, not just passing inspection.



[This message has been edited by kdal (edited 11-22-2005).]

#58831 11/22/05 01:13 PM
Joined: Jul 2004
Posts: 9,923
Likes: 32
G
Member
The only place the code requires the 1.25" setback is next to framing members.
I don't like it, or even agree but that is the way it reads and the way it gets enforced here.
A agree with your concern on service entrance conductors. I would probably go after that with 250.30(A)(1)
<service disconnect shall be>... "nearest the point of entrance of the service conductors." and tell them the "up" has to happen outside the building with the penetration right behind the service disconnect.


Greg Fretwell
#58832 11/22/05 01:22 PM
Joined: Jul 2002
Posts: 717
M
Member
We have a couple of inspectors that won't allow that method on 2x4 construction walls for anything bigger than #2 ser. The minimum bending radius for Ser cable is based on the outside dimensions of the cable, not the conductors. With 4/0 cable you won't be able to make a small enough bend to meet code and stay inside the wall at the same time. See 338.24.