ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Increasing demand factors in residential
by gfretwell - 03/28/24 12:43 AM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
Do we need grounding?
by NORCAL - 03/19/24 05:11 PM
240V only in a home and NEC?
by dsk - 03/19/24 06:33 AM
Cordless Tools: The Obvious Question
by renosteinke - 03/14/24 08:05 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
1 members (gfretwell), 32 guests, and 14 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Page 4 of 4 1 2 3 4
Joined: Jul 2002
Posts: 241
S
SJT Offline OP
Member
Scott, Good drawings. Did you create those on Autocadd? Thanks

Joined: Oct 2000
Posts: 2,723
Likes: 1
Broom Pusher and
Member
SJT,

Yes, the drawings posted here at ECN were compiled within an AutoCAD Environment (drawn with AutoCAD).

BTW:
In regards to...
Quote

I have to check the size of those Primary fuses, to make sure it's under that 125%.


Did you ever find out what size fuses were installed for Primary OCPD?

Let me know if there are any questions or comments.

Thanks for the reply. thanks beer

Scott


Scott " 35 " Thompson
Just Say NO To Green Eggs And Ham!
Joined: Jul 2002
Posts: 241
S
SJT Offline OP
Member
I have not checked the Primary fuse size, but I will. The Bldg. is only 2 years old, and the original design should of had 3 circuits to the cubicle sections. there are 2 sections we will be running an additional circuit to each. Learned a few things about cubicle pre-fab modular wiring on this one. Think I'll open a Sam Adams cold one.