ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals

>> Home   >> Electrical-Photos   >> Classifieds   >> Subscribe to Newsletter   >> Store  
 

Photos of the Week:

Meter vs Bricklayer
Meter vs Bricklayer

Advertisement:-Left
Recent Gallery Topics:
What in Tarnation?
What in Tarnation?
by timmp, September 10
Plumber meets Electrician
Plumber meets Electrician
by timmp, September 10
Who's Online Now
0 members (), 20 guests, and 12 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Joined: Jan 2005
Posts: 5,476
Likes: 3
Cat Servant
Member
I've been presented the oppurtunity to take over a job. That is, the customer is not happy with the current EC - I suspect he doesn't like the prices.

I'd like to hear your thoughts of the ethics of the issue.

Horizontal Ad
Joined: Jan 2002
Posts: 1,457
E
Member
Not knowing the whole situation I'll just say I'd have no problem doing it.

Joined: Mar 2004
Posts: 947
T
twh Offline
Member
Unless you check with the other contractor, you are only getting one side of the story. Sometimes it's the contractor who is refusing to return.

Also, when you take over the job, you also take responsibility for the other guy's work. For example, if his wires are too small, you have to replace them.

There are no ethical issues. Just make sure you get paid.

Joined: Jul 2004
Posts: 10,006
Likes: 37
G
Member

You didn't say what phase the job was in.
If there is a significant amount of uninspected work, I would call for a "partial" inspection on the work done before you put your name on the permit. The inspector may be able to shed some light on what is going on if there were problems.


Greg Fretwell
Joined: Jan 2005
Posts: 5,476
Likes: 3
Cat Servant
Member
Those are very good thoughts.

If nothing else, the city here seems to discourage this situation. First, their fee is nearly a grand to re-issue the permit.

Second, if the EC signed off on the electrical, I'd have to submit my own drawings for the permit.

Joined: Jul 2004
Posts: 10,006
Likes: 37
G
Member
Here in Lee County Fl they are pretty easy going about changing a sub on a permit. I think the fee is only $35 (maybe $50, they did just up some fees). You do not need to resubmit the plans.


Greg Fretwell
Joined: Jul 2007
Posts: 264
W
Member
I would go the partial inspection route, and take lots of pictures to document what shape the job was in when you took over. As far as ethics, I do not see a problem, unless you are friends with the other EC. You are assuming responsibility for any work that is already covered up, if you know the other ECs work is good than you have no worries.


Jimmy

Life is tough, Life is tougher when you are stupid
Horizontal Ad

Link Copied to Clipboard
Advertisement:-Right


Tools for Electricians
Tools for Electricians
 

* * * * * * *
2023 National Electrical Code (NEC)
2023 NEC + Exam Prep Study Guides Now Available!
 

Member Spotlight
sbi
sbi
indiana
Posts: 47