ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals

>> Home   >> Electrical-Photos   >> Classifieds   >> Subscribe to Newsletter   >> Store  
 

Featured:

 Electrical
 Clearance

 *
 Tools
 *

 Books

 *

 Test Equipment

 

Advertisement:-Left

AE-Gifts, Affordable Everyday

Recent Gallery Topics:
What in Tarnation?
What in Tarnation?
by timmp, September 10
Plumber meets Electrician
Plumber meets Electrician
by timmp, September 10
Who's Online Now
0 members (), 191 guests, and 13 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#159076 10/20/06 08:06 PM
Joined: Mar 2002
Posts: 125
S
Member
Talked to a GC today. Ihave not seen him in years. We were talking he asked me what I charge for sq ft on new construction. I have not done that kind of pricing before. Normally look at prints and give price from there. Any help on what to include on this, like service, cans,uc lighting.This is in CT. Thanks Sam

Horizontal Ad
#159077 10/20/06 09:27 PM
Joined: Aug 2005
Posts: 251
T
Member
Go through your paperwork on old houses and get the average sq. ft price.

Ussually when I do it. Its the 'wired to code' price, no extras. Recess, wells, uc lgts ect. all at additional prices.

I havent done it in awhile, last time I did was when copper was at its max price I think I was using around $2.5 sq. ft... lower copper price was 2.2 .. I could be off been awhile


Shake n Bake
#159078 10/21/06 07:07 AM
Joined: Mar 2002
Posts: 125
S
Member
That seems kind of low. At almost $90.00 for 12-2RX and $130.00 14-3 RX. Material alone would run about $2000.00 not including a service.

#159079 10/23/06 10:08 PM
Joined: Aug 2005
Posts: 251
T
Member
Yup, might be low I just did a quick figure.
2200sq.ft
$3000 material
<48 man hrs.
$52 an hour.

residential production sucks... better upsell em.


[This message has been edited by Trick440 (edited 10-23-2006).]


Shake n Bake
#159080 10/23/06 11:40 PM
Joined: Jul 2005
Posts: 17
Likes: 1
W
Member
48 man hours for 2200 square - hate to compete against that - what do you figure on the trim?

#159081 10/24/06 05:21 AM
Joined: Mar 2002
Posts: 125
S
Member
What I can up with is about $7.40 a sq ft.
Figure 2 guys
total 80 manhours
plus $3000 material.
@$65.oo per man

#159082 10/24/06 01:29 PM
Joined: Aug 2005
Posts: 251
T
Member
We have 2 guys finish up to 3000sq ft in 16-20 man hrs.

Now throw in a few cieling fans and a couple complex chandeliers and its longer.

[This message has been edited by Trick440 (edited 10-24-2006).]


Shake n Bake
Horizontal Ad
#159083 10/24/06 09:02 PM
Joined: Aug 2005
Posts: 47
T
Member
I did a house recently and bid per sq ft at 4.50 to min code requirements. 1800 sq ft. I spent more time there than i would like to say, and barely made 4000.00 guys are doing houses for to cheap where i live


Link Copied to Clipboard
Advertisement:-Right
Member Spotlight
RonKipperDatacom
RonKipperDatacom
Kansas City, KS
Posts: 30
Joined: January 2013
Top Posters(30 Days)
dsk 1
Popular Topics(Views)
561,583 Are you busy
435,235 Re: Forum
404,033 Need opinion
Powered by UBB.threads™ PHP Forum Software 7.7.5