iwire

I would say that work associated with certain commercial/residential service taps, etc would fall under "

"infeasible due to equipment design or operational limitations"

You can't have the POCO pull the cut-outs on a pole that may service one or more commercial building to remove/relocate a 200A meter or the like. Same thing with doing service entrance work in a Multiple Dwelling Unit - Apartment or the like.

I would say that shutting down service at the pole to 20 or so apartments or mixed use commercial to replace a main breaker or relocate a meter etc, is "infeasible due to equipment design or operational limitations"

But I AM saying that the work could/can and is performed with proper training & PPE.


PS - When I say "Main Breaker" I mean a Main Breaker on a tenant panel/meter, or of a service submetered from the main service.

[This message has been edited by NJ_WVUGrad (edited 01-29-2007).]