"In this area (NJ) you may be considered as 'giving the ranch away'"
____________________________________________

Around here that would be a handyman price, or a price from a maintance electrician, doing non-permited moonlighting work.

I don't see how anyone can price a job using per opening as a basis, it is nothing more then dart board pricing, a good guess, win some, loose some.

Sq foot method may work for production jobs, where conditions are predicted, or sq ft is good for estimating a budget figure, but to price a job with either method, is shoot from the hip pricing.

A good way to estimate these jobs, is to walk the job, and note the site conditions, then using good job data like previous job actuals, figure the time required to install this job, with what ever conditions exist, and don't forget to include your planning time, and the time it takes to schedule, and the time to return for finish work, and time to fill out and file the permit, in the area i work, your price would be ok, for just the rough work, but every area has it's local economy to consider, and each EC has varied labor, overhead, and profit, so there is no standard cost for any job.



[This message has been edited by LK (edited 09-05-2005).]