how many of you have done a job on a site and then been told that the drawings that they supplied are the wrong ones and now you have to re do the whole job?

i was contracted to replace 13 Mercury low bay lights in a paint and paper supply house.

so we go to the site rope off and make safe the area we are working on and proceed to remove and replace the fittings.

the manager at the end of the day thanks us for an excellant job, we get a signature, go back to the office, agood day was had.

we invoice the job and get paid.

then i get a call from there head office and was requested to meet them on the job.

the man produces a drwing, it dont look nothing like mine., he says this is the one we should have used, we had a small heated discussion and i end up having to re do all the work again, and they dont wanna pay.

our conpany lawyer is now dealing with it.

any body else had this sort of problem and what did you do about it??

britspark