Besides the 4-½" Duct size Note (obviously an error), I have never done (or even seen) any permanent installs with the KWH meter at the PoCo Transformer.

Is this a "Non-California" thing?

As Scott (Electure) knows - along with the other So. Cal. Members here, rarely do we install Secondary Feeders to the PoCo Transformer Vault - or even pole via Riser Ducts.
Anaheim is one area where we do install Secondary Feeders between the PoCo's Transformer Vault / Riser at the Pole, and the Pull Section of the main service / Switch Gear.
Other areas, we just provide Primary and Secondary side Ducts with pull ropes (mandrell ducts too), and the PoCo does the rest.

Also, the Duct requirements are given by the PoCo - as mentioned by Scott (Electure).

Gotta love that GES!!! Quite an elaborate setup, isn't it!

Scott35

p.s. Forgot to mention this also includes purchasing + setting the Transformer Vaults, GES at the Vaults, and all the required stuff for the Primary and Secondary Feeder Ducts per the PoCo's request.
This includes Anaheim also! [Linked Image]

Did some Primary Feeder Underground Ducts on a rather steep hill once. Was really "Fun" putting the Sand and Gravel in for the Cushion! (Fun Read: PITA!!!).

Gluing the Ducts was less fun - trying to keep the can from rolling down the hill became an art form!

Keeping from "Getting High" on the fumes, then rolling down the hill, was a concern too... [Linked Image]

Wasn't around when (if) the Concrete got pumped into the Trench for the Primary Ducts - busy playing around on some other Projects...

Scott35

Returned and edited to add the above stuff.

[This message has been edited by Scott35 (edited 03-21-2004).]