Not all meter sockets have them. The bypass lever is used when changing out a meter. It allows the meter to be pulled without interrupting the downstream load, and is sometimes coupled to the jaws in such a way as to clamp/unclamp the meter blades when operated. The bypass lever also shorts the secondaries of CTs on CT operated meters to prevent high voltages from being developed.
The handle is arranged in such a way as to prevent the enclosure cover from being closed/sealed with the meter bypassed.