ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
Shout Box
Recent Posts
Extension cords
by annemarie1. 09/25/18 06:06 PM
220/230/240V 60Hz Systems
by gfretwell. 09/23/18 02:50 PM
Inspection camera help
by petey_c. 09/22/18 07:52 AM
Motion detectors and dimmers
by gfretwell. 09/20/18 04:02 PM
Acronis Backup 2017
by gfretwell. 09/16/18 12:46 AM
New in the Gallery:
Plug terminals
Housebilding DIY wiring
Who's Online Now
0 registered members (), 26 guests, and 25 spiders.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Fire Pump wiring Art 695 #99556
08/14/06 07:07 PM
08/14/06 07:07 PM
Y
Yoopersup  Offline OP
Member
Joined: Mar 2003
Posts: 849
Michigan
When a Fire pumps Fed from Mulitple sources (Generator- Power Company) the way I read it both sources are required to comply with 695.6 (B) 1 or 2 or 3 . Any input on this Please. Both Generator and Power company sources are remote from Fire Pump control transfer switch & controller.

2017 / 2014 NEC & Related Books and Study Guides
Re: Fire Pump wiring Art 695 #99557
08/14/06 09:06 PM
08/14/06 09:06 PM
G
George Little  Offline
Member
Joined: Jan 2004
Posts: 1,489
Michigan USA
Ernie- I'm far from being the Firepump Guru on this Board but there aren't any exceptions that I read so my answer is yes both supplies must comp[y with 695.6(B) 1 or 2 or 3.

Hey ask easier questions like "What color is a green ground screw?"

See Ya in TC


George Little

Featured:

2017 Master Electrician Exam Preparation Combos
2017 NEC Electrician
Exam Prep Combos:
Master / Journeyman

 

Member Spotlight
RH1
RH1
California
Posts: 22
Joined: August 2009
Show All Member Profiles 
Top Posters(30 Days)
Admin 13
BigB 4
Popular Topics(Views)
249,467 Are you busy
187,384 Re: Forum
176,726 Need opinion
Powered by UBB.threads™ PHP Forum Software 7.6.1
(Release build 20180101)
Page Time: 0.017s Queries: 14 (0.004s) Memory: 0.9425 MB (Peak: 1.0599 MB) Zlib enabled. Server Time: 2018-09-26 02:50:44 UTC