ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals

>> Home   >> Electrical-Photos   >> Classifieds   >> Subscribe to Newsletter   >> Store  
 

Advertisement:-Left
Recent Gallery Topics:
What in Tarnation?
What in Tarnation?
by timmp, September 10
Plumber meets Electrician
Plumber meets Electrician
by timmp, September 10
Who's Online Now
0 members (), 138 guests, and 30 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#40935 08/09/04 08:25 PM
Joined: Mar 2004
Posts: 76
M
Member
I am bidding on a Job, that involves the installation of a 7 KW, Natural Gas fueled generator.
This is the type sold at the Big Blue Box.
It seems like a fairly easy install, but I was wondering if anybody has had any experience with these, & how you went about pricing the job ?
I will be responsible for getting a Lic Plumber to hook up the Gas, and will test it, etc.
Thanks in advance !!!

Horizontal Ad
#40936 08/09/04 11:53 PM
Joined: Jul 2003
Posts: 394
B
Member
Check out the requirements for transferring the load from line to genset carefully. Those components are all special and usually pricey. You don't want to miss something there and have to eat it.

#40937 08/09/04 11:59 PM
Joined: May 2003
Posts: 2,876
E
e57 Offline
Member
Check the gas pressure spec's, it may require additional regulator at the main line. (Require more pressure for the engine)

Where the city will allow you to put it...

Not cool on small lot neighborhoods, bugs the neighbors... It runs once a week for twenty minutes.

Maintenace, oil changes and the like.

Then the electric stuff. Then bid it.


Mark Heller
"Well - I oughta....." -Jackie Gleason
#40938 08/10/04 04:04 PM
Joined: Jun 2004
Posts: 220
T
Member
If it is a Generac/Guardian system, the typical pre- packaged system takes about 3-4 hrs to do. Make sure to put the generator 3 ft. from any combustible materials( like the house). also, should try to get as close as possible to the main panel. the genarator requires 11-14" water column pressure, NG or LPG. this usually requires a seperate regulator. If you postion the unit right, there is little in extra material to get. An annual maintenence agreement is a great way to make additional revenue from generator sales. Look at around 1-2 hrs(depending on liquid or air cooled) for annual maintainence.

#40939 08/11/04 01:48 AM
Joined: Mar 2004
Posts: 76
M
Member
Thanks for the Info, I hadn't thought about yearly Maintenance !!!


Link Copied to Clipboard
Featured:

 Electrical
 Clearance

 *
 Tools
 *

 Books

 *

 Test Equipment

 

Advertisement:-Right
Member Spotlight
CharlieE
CharlieE
Indianapolis
Posts: 201
Joined: April 2004