ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals

>> Home   >> Electrical-Photos   >> Classifieds   >> Subscribe to Newsletter   >> Store  
 

Featured:

 Electrical
 Clearance

 *
 Tools
 *

 Books

 *

 Test Equipment

 

Recent Gallery Topics:
What in Tarnation?
What in Tarnation?
by timmp, September 10
Plumber meets Electrician
Plumber meets Electrician
by timmp, September 10
Who's Online Now
0 members (), 243 guests, and 19 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#213441 05/01/14 11:54 PM
Joined: Feb 2008
Posts: 193
S
Member
I spoke to my brother in law who is a builder in Knoxville. His electrician is responsible to install the service line to transformer with an underground service. He will trench and bring the wires into tho transformer for the poco to land. Where I live, the poco is responsible from the meter to the transformer. How many of you have to take your install to the poco transformer?

Tools for Electricians:

Tools for Electricians, Installers & Maintenance Technicians

Joined: Jul 2004
Posts: 10,035
Likes: 37
G
Member
Down here the customer is responsible for getting the UG lateral in but FPL will do it on a contract cheaper than most builders think they can hire an electrician to do it, so they just pay FPL.
If FPL does it the AHJ usually doesn't even inspect it. (other that what you see in the meter can)


Greg Fretwell
Joined: Jul 2007
Posts: 264
W
Member
In my area the poco comes to us, we set the meter, get the inspection then the poco trenches and installs the lateral. On overhead services the poco handles everything past the weatherhead, we leave about 24 inches of wire out of the weatherhead for them to make a connection to.


Jimmy

Life is tough, Life is tougher when you are stupid
Joined: Dec 2000
Posts: 4,294
Member

In SoCal the Contractor is responsible for the complete UG duct installation, and the POCO inspectors approve the installation before backfill. After backfilling, a mandrel test may be required. The electricians pull the mandrel in the inspector's presence.

The POCO supplies the cable, pull the cable, terminates it, and install the meters. (They have separate crews that for all of these tasks)




Joined: Apr 2002
Posts: 7,413
Likes: 9
Member
NJ style in PSE&G area:
UG in an overhead area, EC installs conduit and wire to pole; 10' Sch 80 at pole, with wire to reach the OH drop.

OH in a BUD area, POCO does all to line side of meter pan. EC supplies PVC under meter pan & bell end.

OH in OH area; EC responsible to weatherhead.

PSE&G supplies meter pans (up to 320/400); drop hooks.

ECs allowed to cut & reconnect all resi service upgrades.



John

Link Copied to Clipboard
Powered by UBB.threads™ PHP Forum Software 7.7.5