ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
Shout Box
Recent Posts
Recall Notice Kidde Smoke Alarms
by dougwells. 03/22/18 01:40 PM
by HotLine1. 03/22/18 09:08 AM
Recall notice: Southwire wi-fi wall switches
by sparkyinak. 03/15/18 06:03 PM
Goodman Manufacturing Recalls Modular Blowers
by Admin. 03/13/18 10:40 PM
New in the Gallery:
Housebilding DIY wiring
SE cable question
Who's Online Now
1 registered members (dougwells), 51 guests, and 8 spiders.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
installing service lines #213441
05/02/14 12:54 AM
05/02/14 12:54 AM
schenimann  Offline OP
Joined: Feb 2008
Posts: 193
Western North Carolina
I spoke to my brother in law who is a builder in Knoxville. His electrician is responsible to install the service line to transformer with an underground service. He will trench and bring the wires into tho transformer for the poco to land. Where I live, the poco is responsible from the meter to the transformer. How many of you have to take your install to the poco transformer?

Work Gear for Electricians and the Trades
Re: installing service lines [Re: schenimann] #213442
05/02/14 01:48 AM
05/02/14 01:48 AM
gfretwell  Offline

Joined: Jul 2004
Posts: 9,186
Down here the customer is responsible for getting the UG lateral in but FPL will do it on a contract cheaper than most builders think they can hire an electrician to do it, so they just pay FPL.
If FPL does it the AHJ usually doesn't even inspect it. (other that what you see in the meter can)

Greg Fretwell
Re: installing service lines [Re: schenimann] #213443
05/02/14 09:00 AM
05/02/14 09:00 AM
wire_twister  Offline
Joined: Jul 2007
Posts: 265
Georgia USA
In my area the poco comes to us, we set the meter, get the inspection then the poco trenches and installs the lateral. On overhead services the poco handles everything past the weatherhead, we leave about 24 inches of wire out of the weatherhead for them to make a connection to.


Life is tough, Life is tougher when you are stupid
Re: installing service lines [Re: schenimann] #213445
05/02/14 05:42 PM
05/02/14 05:42 PM
electure  Offline

Joined: Dec 2000
Posts: 4,265
Fullerton, CA USA

In SoCal the Contractor is responsible for the complete UG duct installation, and the POCO inspectors approve the installation before backfill. After backfilling, a mandrel test may be required. The electricians pull the mandrel in the inspector's presence.

The POCO supplies the cable, pull the cable, terminates it, and install the meters. (They have separate crews that for all of these tasks)

Re: installing service lines [Re: schenimann] #213446
05/02/14 10:27 PM
05/02/14 10:27 PM
HotLine1  Offline

Joined: Apr 2002
Posts: 6,936
Brick, NJ USA
NJ style in PSE&G area:
UG in an overhead area, EC installs conduit and wire to pole; 10' Sch 80 at pole, with wire to reach the OH drop.

OH in a BUD area, POCO does all to line side of meter pan. EC supplies PVC under meter pan & bell end.

OH in OH area; EC responsible to weatherhead.

PSE&G supplies meter pans (up to 320/400); drop hooks.

ECs allowed to cut & reconnect all resi service upgrades.



2017 Master Electrician Exam Preparation Combos
2017 NEC Electrician
Exam Prep Combos:
Master / Journeyman


Member Spotlight
Bakersfield, CA (Originally Orange Co.)
Posts: 1,431
Joined: February 2004
Show All Member Profiles 
Top Posters(30 Days)
Admin 5
Trumpy 5
Popular Topics(Views)
244,700 Are you busy
181,815 Re: Forum
171,860 Need opinion
Powered by UBB.threads™ PHP Forum Software 7.6.1
(Release build 20180101)
Page Time: 0.024s Queries: 15 (0.004s) Memory: 0.9690 MB (Peak: 1.1113 MB) Zlib enabled. Server Time: 2018-03-22 17:57:31 UTC