ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals

>> Home   >> Electrical-Photos   >> Classifieds   >> Subscribe to Newsletter   >> Store  
 

Featured:

 Electrical
 Clearance

 *
 Tools
 *

 Books

 *

 Test Equipment

 

Recent Gallery Topics:
What in Tarnation?
What in Tarnation?
by timmp, September 10
Plumber meets Electrician
Plumber meets Electrician
by timmp, September 10
Who's Online Now
0 members (), 313 guests, and 22 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#202028 07/11/11 11:37 AM
Joined: May 2010
Posts: 30
B
Bravo Offline OP
Member
Hello,

I have an existing emergency power dist. system with life safety & non-life safety loads. There is a requirement to add new life safety branch circuits. The existing emer. pwr system currently does not have overcurrent devices selectively coordinated.

Once we modify the existing system, is a coordination study required per NEC 700.27? The system was designed and constructed prior to 2005 NEC.

Thanks in advance.

Work Gear for Electricians and the Trades

Workgear for Electricians

Joined: Apr 2002
Posts: 7,413
Likes: 9
Member
dbravo:

I would discuss your situation with the AHJ in the town the project is in.

The extent of the mods you have to perform may be the deciding factor.



John