In IL.: We set the meter base OH/UG and panel, two 20A breakers, two GFI'S. These are at the panel location on wall or panel depending on inspector. Utility is typically called by GM, the insall is done when GM contacts us and schedule is set. AHJ signs off on install, utility will run wire, hook, install meter, fire-up. We do service and don't go back until the house is ready for electric rough.
As to a temp. on a 1st or second floor, size of house is a factor, typical house 5000 sq.ft., base, 1st, 2nd, they get the panel and one GFI on 2nd floor after we are done with rough. Typical is this is a curteousy of the company to the GM, of course the $$$$$ for the work is built in to the overall job. We just hook to a dedicated circuit, such as a whirlpool/bath so the hot isn't in too many openings for the drywallers, and less areas we have to protect the bare ends of wires. [Linked Image]