Rat:
I know what you mean. With my AHJ hat on, I get a few 'not ready' cause the GC/Builder/etc thought it was time.

On the other side, we have quite a few jobs that the EC's 'forgot' to call/schedule or follow-thru on the inspection requirements.

Amazing how many skeletons are in the file cabinets. NJ Law says "EC is the responsible person to obtain all required inspections and approvals". Also, 13:xxx states that the consumer is NOT to make final payment to the contractor until 'final' inspections and approvals are obtained.