I am still at a loss as to why the masons are running the job.

Look right across the table and say fine, I will bill for all costs above straight time, or I will bill for the time to fish them after.

The office I work for would not expect any less of me and would support this move.

The project manager would follow up with letters stating the same to the GC.

Now it is up to the GC to decide if he wants to slow the masons or pay the plumbers & electricians.

Be a squeaky wheel because if you do not make waves you will continue to be abused during the whole project.

I do not mean uncooperative but don't take any grief either.


Bob Badger
Construction & Maintenance Electrician
Massachusetts