Hi,
There is a piece of rebar sticking out of the hole. They missed the steel and ran schedule 80 over to bug onto the steel. it is in the walkway and we do not want to buy it...but contractor refuses to fix. I suggested core drilling down to rebar and bugging on there..

poor quality work for sure..

it is coming up through the slab and a nipple from a 4/0 ground...the green is #2.

thanks

Greg