Scott35:
Man, that sounds like a first class install.
Last one we did:
two circuit IG plugmold; 6" oc; 6' length
twelve receptacles total at each location.
Quad GP receptacle in lower kick area.
Wouldn't ya know.....the computer installer comes in with the power strips and plugs into the GP quad & daisy chains the strips.
AHJ shows for final, sees the strip chains and has a fit! Told him "by others"; waste of breath. Had to get computer guy back, straighten him out, and reschedule inspection.

BTW, We do the TVSS at the panels also.