Yeah, back to back no Disconnect (w/ Main CB), not back to back, must have disco (W/ main CB)...
Did I clear my muddling up a little?
<in jest>
(Listen to what I mean, not what I say...)</in jest>
The 400 ft run had a Main CB/ Disco adjacent to the meterbase, so technically, it was a "feeder" and not a "service".
Still a long run.
My longest run was 600 ft. of 1/0 Cu for a 240V 30A feed for a cell tower repeater.
That pull was a nightmare... I had used 2" PVC instead of 3" and will never do that again.