We are currently working on a job that has awful plans (to say the least) and the general contractor and the owner have teamed up to make us responsible for any and all omissions by the engineer. Example, plans show 20 emergency fixtures-fire marshal wants 5 additional fixtures-we submit change order for 5 extra fixtures and are told that it was our responsibility to have proper number to begin with! This is just but one example of a string of about 10 similar situations just on this one job! Any advice or input would be greatly appreciated.