Here's a toughy...

I get to keep the temp service for the Full Moon Music Festival, but I have to determine its value to know how much to deduct from their bill.

A UG Meterbase, 3/0 Cu Wire, 200A 20 Space Load Center (Raintite), 20A GFCI WP Receptacle, 2 4"x4"x8' posts with 3/4" Plywood backing, (I even used sealing rings for the PVC Nipple between the MB and LC... Got an odd look from the AHJ on that one! He said the Cu service wire was overkill enough!)

I've got about $350 in materials and about $300 in labor involved, but it has yet to be removed from the temp location.

How much should I give them for it?

I told them I'd try to be fair to both parties.

[Linked Image]

Oh, I'm still being blamed for voltage spikes... Guess I needed to have an Oscilloscope with real time printout...


-Virgil