caselec, Yep, thats the one, great picture. I will then mount the 200a load center on the back side of the house fed from the 400a on the side of the house. The trick is to coordinate the power co to disconnect power, pull in new 4/0 feeders, then after I mount the new panel, have it inspected by the city, then reconnected by the power co - all in one day.
The Golden Rule - "The man with the gold makes the rule"