I ended up running 3/4 inch EMT. I supported it on 10 inch lengths of treated 4X4 every 5 feet. I gooped the wood to the roof and secured the EMT to the wood with one hole straps. I used compression type couplings and TA's. I'm tempted to spray the compression fittings and the straps with zinc to seal them and prevent future rust. Is this overkill?
The sign contractor wanted 3-20 namp circuits and he wanted me to run #10 wire since it was over 50 feet from the panel. I ran 5#10's (black, red, blue, white and green) from the 120/208 volt 3 phase panel. I installed a 3 phase 20 amp breaker in the panel. On the roof I installed a 3 phase main lug panel with 3 single phase breakers. I also installed a GFCI fed by a seperate breaker on phase A. Have any of you installed a flood light for repairman's convience?
Where I penetrated the tarred roof I gooped it wirth mastic. I told the customer to have his roofing contractor check it. That's about it.
bob