Ghost:

I get your points on 'slack'. As I said there are real world solutions (NEC Compliant) to solve issues. For the OPs issue, he should have the issue addressed by the design professional of record. A triad rod setup, ground plate, ground ring, or chip the footing may be required. A 2k service, and a 200K SF warehouse must have approved plans and specs by the local AHJ office.

Let me ad that I slipped off the sizes of the service and building with my previous comments, not realizing the size of the project. I still believe there are solutions to any issue.


John