Usual scenario is...
Frame
Roofing
Windows/Doors (temp)
HVAC
Plumbers
Electricians
ROUGH INSPECTIONS: Elec/Plumb/Fire
Framing inspection
Insulation
Insulation Inspection
Mix a few 'red tags' inbetween......
The alarm, A/V, Comm slip in accordingly.
No wiring is installed before the structure is weather tight. Very few have tried, none have been successful...