I've had decent success telling them that it will take a period of hours to replace a failed component, during which time they will be out of action.
If they schedule it, they can decide when that outage will occur; if not, the outage will occur whenever it wants to happen, even if that's their busiest time of the day/month/year.

Once I convince them that there definitely WILL be an outage, most of them opt to have it be scheduled instead of being a complete surprise. Besides, if it's scheduled there's a better chance that I won't get stopped partway through the work because I need to run and get parts.

Remember: Murphy was an optimist.


Ghost307