A GEC from the panel terminates to the water pipe, then a bonding jumper from the water pipe terminates on the ground rod. One of my colleague says it is a violation because it has to be one continuous piece from the panel to the water pipe then to the ground rod.
I say the only portion that has to be continuous is the GEC not the bonding jumper that is to the ground rod.