I'd suggest that you don't bid the job until you have a complete set of plans.
Ditto!!!
Besides the Indoor Lighting Compliance forms being required for this T.I., there are a few other things the Building Department will want compiled to a Plan Set:
- Single Line,
- Load Calcs,
- Panel Schedule(s),
- Lighting Plan,
- Power Plan,
- Lighting Control details.
The best suggestion I could give is to request a complete set of Electrical Plans, which have been approved by Plan Check.
If you feel comfortable, you could perform Design/Build ... but that is another thread!
Scott