An excellent question this.
I was recently hired ot perform trim-out on a job that had been abandoned by a flakey EC (yes, I know all the pitfalls) and encountered this exact situation - the guy had ignored the detail on the plans and set the hood outlet directly behind where the hood was going. I considered all options, then finally decide to replace the entire wire run to avoid leaving a junction behind the hood. This required cutting out drywall for the 15' to the last accessible junction point.
On the other hand, I've seen a spa-type tub installed with the outlet and motor inaccesible without removing the entire tub, and to amazement, it passed. I guess it all comes down the inspector and his/her intrupretation of teh rules.