2 guys 10per/hr= $20
1 electrician $50per/hr=$100.
$120. to do job
This is if the scafolding is owned and doesn't need transportedand is only one or 2 units needing service.
For example I do lots of work for a private school and they have maintance personal that would set this up for me and all I would do is climb up there and change the ballast. Heck I think the guys might even be salary. Or I could rent boom truck or lift for $250. for 1 day or $750 a week., and I would have to pick it up. or pay $50 for delivery and $50 for pickup.
I just went through this with them about 3 weeks ago. However I did end end up with the lift as we came up with some other projects to use it on. Like fix the ball on top of flag pole. Troubleshoot riding rink lights and some others.
Ob