The GC kept a very clean site and we would help to do that too. [Linked Image] [Linked Image]

Along with the obvious safety factor of a clean job site, I believe it helps the attitude (clean, professional, etc) of the workers (myself included) speeding the job along.

The pipe run is for the cabling contractor, it was part of our contract to provide 3/4" raceway up to the ceiling.

We used about 1500 cable supports and every box is a 4" sq deep with a box support.

How many of you do like we do and use 3/4" raised rings for 5/8" Sheetrock.

It makes the ring flush with the drywall and gives great support to the devices. [Linked Image]

By the way, if the walls where not going to be sound insulated with fiberglass batts we would have anti rattle clips on the MCs where they pass through the studs. [Linked Image]


Bob Badger
Construction & Maintenance Electrician