Clydesdale, as far as the service, do you mean indoor panel or outdoor disco? We only make up the SER in the panel on rough. We land the branch circuits when we return for permanent power.

It takes a man just over an hour to make up the panel and install the breakers for a 150 or 200 amp panel. Of course 300 and 400's take more time.

As for the outside service, we use a meter/main combo on the 150's and 200's. The quickest time so far 27 minutes. That's mount the meter make up the service cable, drive the rod (just one here), connect the GEC, drop the chase pipe and and strap the pipe. What can I say, my guys like to race.