I lost a bid job a decade back that still burns me up quite a bit. It was a rooftop package exchange job- several large units. The specs clearly stated rigid 2" and 3" conduits be run out to the units. I submit my bid and hear back that I was "way too high" compared to the next company. About a year later I was back up on that same roof to do a service work job and what did I get to see? EMT conduits, with set screw fittings no less out in the weather. And to top it, I know there was a permit pulled and so therefore in theory an inspection done.....

Last edited by macmikeman; 08/08/07 12:51 PM. Reason: changed ss to set screw to clarify not stainless steel