The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!


2017 NEC and Related
2017 NEC
Now Available!

Recent Posts
Parking lot pole light swap....
by gfretwell
10/24/16 08:46 PM
International Wire Colour Codes
by Tjia1981
10/23/16 12:08 PM
Son of Sparky
by HotLine1
10/20/16 07:43 PM
Speaking of Plugmold ...
by gfretwell
10/17/16 02:37 PM
Broken battery charger? Check for cobwebs!
by gfretwell
10/17/16 02:30 PM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 14
HotLine1 7
ghost307 7
renosteinke 6
Potseal 4
Who's Online
1 registered (gfretwell), 313 Guests and 3 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#157114 - 08/17/05 05:46 PM Integrety #5: Plan review
renosteinke Offline
Cat Servant

Registered: 01/22/05
Posts: 5305
Loc: Blue Collar Country
You're looking at the plans for a job, and you see something has been overlooked- or just won't work as drawn.

Do you tell this to the customer now- or do you wait until you get the job, then put in fo a change order? Or- just do what you were told, and let them figure it out?

Business, Office, Estimating, Legal:
#157115 - 08/19/05 10:26 PM Re: Integrety #5: Plan review
sierra electrician Offline

Registered: 02/12/05
Posts: 220
Loc: North Fork, CA USA
Everything up front, unless...... the guy's your bidding aren't asking the same questions. In that case bid it flat and pick up the "extra"

On competive bids you usually only have until the last two weeks to get your RFI's answerd. If you get them in in time the Architect will send out addendum's reflecting the changes so all bids will be equal.


#157116 - 08/21/05 07:18 AM Re: Integrety #5: Plan review
Tiger Offline

Registered: 05/04/05
Posts: 714
Loc: Crystal Lake, IL USA
It depends what kind of plan I have and how much time I want to spend on it. For an existing client I bring it to their attention and include it in the Contract Proposal. I make a note that says something like "Bid to print with the following additions".

For a price-shopper with a sketch, I add a note that says something like "Bid to print. Plans should be submitted to the local Building Department for Permit and approval."


#157117 - 08/21/05 09:05 AM Re: Integrety #5: Plan review
Electric Eagle Offline

Registered: 04/20/02
Posts: 928
Loc: Alpharetta, GA
It depeds on the situation, but I tend to point these things out. I think it makes my proposal look more complete if I point out mistakes and the fact that I considered them before starting the project. A customer might pay a considerable amount more if they know I'm not going to hit them with change orders.

I personally don't like change orders. I would never submit a low bid to get a job thinking "I'll just make it up on change orders". My regular customers know this and often don't even get competing bids.

#157118 - 08/21/05 03:18 PM Re: Integrety #5: Plan review
LK Offline


Registered: 01/21/03
Posts: 1721
Loc: New Jersey
"A customer might pay a considerable amount more if they know I'm not going to hit them with change orders."


Yes they do, and they usually become your best customers, bringing their attention to errors, and items that were missed, puts you in a much better light, for bringing in the job on, or under budget.