Bob, the service rated is what I was wondering about.

I was pondering changing the meter can, to a service rated one, or mounting a fused disconnect, then the ATS.

The dilema is, the panels are currently 60' away from the meter. The PVC runs around the perimeter of the foundation, and under cobblestone walkways. The basement is finished, so this makes installing the ATS by the panels, almost impossible.

If I install (2) 200a ATS, do I have to somehow interlock them together?


The gas line Joe, is not my problem. That's on his end to have installed. No to the question of POCO going to the ATS, and then the meter. It would stay the meter, then to the ATS, then to the panels.