Greg:
I can explain the Twp permitting process for solar, and hope that some comments are made with respect to this.

Residential: Electrical & Building permit applications required, along with two (2) sets of plans. Engineer signoff required for rack & panels (roof loads). Electrical plan may be by NJ Lic EC. Plan review process by Bldg & Elec usually completed in approx 5-7 days.

However, with the ECs that do not submit correct, compliant plans & application, the 'wait' can take as long as it takes them to provide compliant paperwork.

Comm jobs usually turn around in 7-10 days also.

Fees are excessive or high?? An average resi fees out at $140-$170. The Bldg permit is usually <$100. Two (2) inspections are required (Resi) for each (Elec & Bldg) unless the 'red tag' happens.

Comm fees are hard to 'average', ranges from <$1000 to $15K
Naturally, there are numerous inspections. A <5MW probably had 40+/- inspections.

Excessive fees?? Red Tape?? Comments Please, guys



John