Everything up front, unless...... the guy's your bidding aren't asking the same questions. In that case bid it flat and pick up the "extra"

On competive bids you usually only have until the last two weeks to get your RFI's answerd. If you get them in in time the Architect will send out addendum's reflecting the changes so all bids will be equal.