ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
Top Posters(30 Days)
twh 3
Recent Posts
Nec circuit protection
by gfretwell. 11/21/17 11:01 PM
FPE in Germany
by Texas_Ranger. 11/19/17 07:30 AM
Ceiling fan distance from outdoor hot tub
by gfretwell. 11/16/17 02:18 AM
diazed fuses
by Texas_Ranger. 11/13/17 03:02 PM
Theft deterrent alarm
by gfretwell. 11/12/17 01:39 PM
New in the Gallery:
Gallery Test
Popular Topics(Views)
242,614 Are you busy
178,812 Re: Forum
170,051 Need opinion
Who's Online Now
0 registered members (), 22 guests, and 8 spiders.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate This Thread
#213441 - 05/01/14 11:54 PM installing service lines  
schenimann  Offline
Member
Joined: Feb 2008
Posts: 193
Western North Carolina
I spoke to my brother in law who is a builder in Knoxville. His electrician is responsible to install the service line to transformer with an underground service. He will trench and bring the wires into tho transformer for the poco to land. Where I live, the poco is responsible from the meter to the transformer. How many of you have to take your install to the poco transformer?


Work Gear for Electricians and the Trades

#213442 - 05/02/14 12:48 AM Re: installing service lines [Re: schenimann]  
gfretwell  Offline


Member
Joined: Jul 2004
Posts: 9,136
Estero,Fl,usa
Down here the customer is responsible for getting the UG lateral in but FPL will do it on a contract cheaper than most builders think they can hire an electrician to do it, so they just pay FPL.
If FPL does it the AHJ usually doesn't even inspect it. (other that what you see in the meter can)


Greg Fretwell

#213443 - 05/02/14 08:00 AM Re: installing service lines [Re: schenimann]  
wire_twister  Offline
Member
Joined: Jul 2007
Posts: 265
Georgia USA
In my area the poco comes to us, we set the meter, get the inspection then the poco trenches and installs the lateral. On overhead services the poco handles everything past the weatherhead, we leave about 24 inches of wire out of the weatherhead for them to make a connection to.


Jimmy

Life is tough, Life is tougher when you are stupid

#213445 - 05/02/14 04:42 PM Re: installing service lines [Re: schenimann]  
electure  Offline


Member
Joined: Dec 2000
Posts: 4,262
Fullerton, CA USA

In SoCal the Contractor is responsible for the complete UG duct installation, and the POCO inspectors approve the installation before backfill. After backfilling, a mandrel test may be required. The electricians pull the mandrel in the inspector's presence.

The POCO supplies the cable, pull the cable, terminates it, and install the meters. (They have separate crews that for all of these tasks)





#213446 - 05/02/14 09:27 PM Re: installing service lines [Re: schenimann]  
HotLine1  Offline


Member
Joined: Apr 2002
Posts: 6,874
Brick, NJ USA
NJ style in PSE&G area:
UG in an overhead area, EC installs conduit and wire to pole; 10' Sch 80 at pole, with wire to reach the OH drop.

OH in a BUD area, POCO does all to line side of meter pan. EC supplies PVC under meter pan & bell end.

OH in OH area; EC responsible to weatherhead.

PSE&G supplies meter pans (up to 320/400); drop hooks.

ECs allowed to cut & reconnect all resi service upgrades.



John


Member Spotlight
Joe Tedesco
Joe Tedesco
Boston, Massachusetts USA
Posts: 2,749
Joined: October 2000
Show All Member Profiles 
Featured:

2017 Master Electrician Exam Preparation Combos
2017 NEC Electrician
Exam Prep Combos:
Master / Journeyman

 

Shout Box
Powered by UBB.threads™ PHP Forum Software 7.6.0
Page Time: 0.013s Queries: 15 (0.003s) Memory: 0.7692 MB (Peak: 0.9129 MB) Zlib enabled. Server Time: 2017-11-22 12:46:35 UTC