Posted By: Redsy line=primary, load=secondary - 03/13/02 12:12 PM
I heard someone refer to the line and load terminals of a CB as primary side and secondary side?
Is this common terminology?
Posted By: WARREN1 Re: line=primary, load=secondary - 03/13/02 01:04 PM
Redsy
Don't know if it is common or not, but I have used that terminology when discussing lines and loads with Lead Engineers and some contractors.
Posted By: Joe Tedesco Re: line=primary, load=secondary - 03/13/02 04:41 PM
Redsy:

The UL Directory "White Book" includes the following statement under the heading of "LINE - LOAD CONNECTIONS"

"Line and load markings on a circuit breaker are intended to limit connections thereto as marked."

Watch out four for backfed installations, if you need more information from the "White Book" let me know.

[This message has been edited by Joe Tedesco (edited 03-13-2002).]
Posted By: The Watt Doctor Re: line=primary, load=secondary - 03/14/02 02:59 PM
Never heard of it relative to breakers. Always hear it relative to transformers.

Regards,
Doc