I need to determine the load rating for Square-Duct metal wireway (8"). The electricians walk on the overhead wireways on occassion and the question of whether or not the wireways provide adequate support has come up. I don't see a specification for this in the technical documentaion.
From my research so far, neither NEC article 376 nor maufacturers of wireway list a specification for point loading from personnel walking on the wireways. Can you help me with this question? Thanks.
Bjarney: That is an excellent question! The mfg may give an answer..... It probably will be "we do not intend that it be used for support of personel"
Thinking about this, in the lawyer crazy, suit filled world that we are a part of... implying that an item "could" be used for a purpose, can land anyone in court. I'm not bashing lawyers, but.....
IF it could possibly be approved OSHE probably would require a guard rail, toe kicks, and a tie-down beam!!!