yeah its sat night and being away from home is about as bad...
yes it is a powerhouse...but the voltage is 480vac...
the contractor is not even attempting to follow the nec on the job...
there are a lot of violations around....this is one that i really wanted to be sure on so i figured i would ask for some opinions..they have stacked a couple layers of 500MCM conductors in a 24" tray and i think they are planning on dumping some control cables in there as well as some multi-conductor power cables...3/C 12, etc...
ge requires that the nec be followed if it is on our equipment even if it is a powerhouse...i have never seen a job where the nec was not recognized..
pictures available
thanks for the input