ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat Box
Recent Posts
HVDC Greece to Crete
by gfretwell - 08/06/20 02:28 AM
310.15 (B) 7 Feeders
by HotLine1 - 07/31/20 02:29 PM
What would be the ideal solution?
by Fleppin - 07/21/20 12:42 AM
NESC question
by gfretwell - 07/16/20 04:17 PM
Code Violation or just not good Practice?
by HotLine1 - 07/16/20 03:03 PM
New in the Gallery:
Facebook follies, bad wiring
FPE in Germany pt.2
Who's Online Now
0 registered members (), 13 guests, and 14 spiders.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Transmission lines across freeway... #53291 06/20/05 09:17 AM
Joined: Jun 2001
Posts: 161
M
Mike Wescoatt Offline OP
Member
This is a question for any linemen out there...
How do you get a set of lines across a major interstate freeway? I assume you divert traffic for a while to run a messenger, but what if there is no frontage to divert traffic to? I saw a couple of what looked like 7.2KV 3 phase wye sets run across I-15 and one was where there is nothing but the freeway. Just curious...


Mike Wescoatt
Work Gear for Electricians and the Trades
Re: Transmission lines across freeway... #53292 06/20/05 09:24 AM
Joined: Feb 2005
Posts: 361
C
Celtic Offline
Member
Helicoper is one way.


~~ CELTIC ~~
...-= NJ =-...
Re: Transmission lines across freeway... #53293 06/20/05 11:28 AM
Joined: May 2001
Posts: 717
G
George Corron Offline
Member
You pretty rarely get to shut anything down. The way it's normally done in a busy environment is for a relay of bucket trucks, one on each side of the highway and one in the middle (sometimes you need more, sometimes less).

One bucket has the cable, passes it off to the next and stays there feeding it across, and so on until you have it across and the span is properly "slacked".

Not really complicated, ya just GOTTA remember to have your boom above the 18' level.....or else. [Linked Image]

Re: Transmission lines across freeway... #53294 06/20/05 02:14 PM
Joined: Feb 2003
Posts: 357
M
mbhydro Offline
Member
I have seen it done here in Manitoba where they close off the highway between 11 pm and 5 am to do it.

The last one I remember seeing done took two nights. The first night to get all the lines across and the second night to get the sag set. The contractor set some temporary poles with crossarms in the middle of the median to keep the conductors from falling onto the asphalt as they were pulling them.

Re: Transmission lines across freeway... #53295 06/20/05 03:35 PM
Joined: Jun 2001
Posts: 161
M
Mike Wescoatt Offline OP
Member
Never thought about the set of bucket trucks. That wouldn't be bad for a couple of lanes, but a different story for Salt lake where there are 6 lanes... But you could funnel it down to two lanes on graveyard shift.
Sure beats sending the apprentice across the freeway with a messenger tied to his belt...


Mike Wescoatt
Re: Transmission lines across freeway... #53296 06/20/05 08:05 PM
Joined: Jan 2005
Posts: 5,316
renosteinke Offline
Cat Servant
Member
Would you believe me, if I said we save all such work for September, and the National Baloon Races? :-)

Re: Transmission lines across freeway... #53297 06/24/05 01:41 PM
Joined: Feb 2005
Posts: 693
L
Larry Fine Offline
Member
Umm, no.


Larry Fine
Fine Electric Co.
fineelectricco.com

Featured:

2020 National Electrical Code
2020 National Electrical
Code (NEC)

* * * * * * *

2017 Master Electrician Exam Preparation Combos
2017 NEC Electrician
Exam Prep Combos:
Master / Journeyman

 

Member Spotlight
TOOL_5150
TOOL_5150
Bay Area
Posts: 61
Joined: August 2007
Show All Member Profiles 
Top Posters(30 Days)
BigB 3
Popular Topics(Views)
268,551 Are you busy
202,946 Re: Forum
191,328 Need opinion
Powered by UBB.threads™ PHP Forum Software 7.7.3